Road Construction Underway in and Around the Kality Natural Gas Depot

ADDIS ABABA (AACRA) — November 24, 2026 — Construction of an access road and expansion of the existing roadway leading to the Akaki Natural Gas Storage Depot in the southern part of Addis Ababa is actively underway.

Spanning 2.88 kilometers in total length, the project is being executed through a collaborative approach: contractor Brothers Trading is carrying out construction up to the sub-base layer, while the Addis Ababa City Roads Authority (AACRA) is executing the asphalt paving works through its own in-house workforce.

To date, concrete pavement construction at the natural gas storage depot has been completed, and primary-layer asphalt paving has been laid along one direction of a 560-meter section of the road.

Additionally, earth cutting, embankment filling, and sub-base preparation are underway along both sides of the existing asphalt road to add extra lanes, enabling the corridor to accommodate three vehicles abreast simultaneously.

Upon completion, the road upgrade will streamline mobility for motorists traveling to the Kality city bus depot, the natural gas depot, and neighboring public and private institutions, while significantly improving public transport services for local residents.